DEVELOPMENT OF THE SOUTHERN PART OF THE PORT IS A NEW PERSPECTIVE FOR LITHUANIAN INDUSTRY AND EXPORTS
The aim of the development of the southern port is to allow for the expansion of cargo handling terminals with the possibility to provide additional value-added services and accommodate BALTMAX vessels of maximum parameters, i.e. eventually up to 490 m in length, up to 70 m in with, and up to 15.5 m in draft.
Teaser of Southport Development Project Strategic Market Study Outline
Parameters of the new port
A new container terminal will be built on a newly created 100 ha area and marine engineering industry activities will be carried out. The Southern Marina, i.e. a small and recreational craft harbour, is also planned as an important contribution to the city’s infrastructure development.
PROGRESS
03/2021 – 02/2022
Preparation of project proposals

02/2022 – 06/2022
Evaluation of project proposals (from a navigational point of view)

07/2022 – 02/2024
Environmental impact assessment, hydrodynamic modeling

08/2024 – 12/2023
Preparation of the market study for the development of the southern part of Klaipeda State Seaport

05/2024 – 11/2024
Market consultations with potential investors

since 08/2024
Engineering Geological and Geotechnical Investigations

since 12/2024
Public Procurement Procedures for selecting construction design proposals

since 06/2025
design proposals and permit to build

05/2026
contract with a transaction advisory

05/2026
CONTRACT WITH the southern breakwaters construction COMPANY

Investments
The preliminary infrastructure investment is estimated at €600 million.
LOCATION


Hinterland connectivity
- Southern bypass connecting Southport with highway A1
- Railway station designated for the supply to the Southern Port